REPORT
ON
PROTOTYPE
TESTING OF REPAIR TECHNIQUES
FOR
REPAIR OF EARTHQUAKE DAMAGE
TO
LOS
ANGELES CITY HALL
EXTERIOR
WALLS
UNDER
CONTRACT
DACW09-72-0067
PREPARED
FOR
LOS
ANGELES DISTRICT CORPS OF ENGINEERS
PREPARED
BY
VTN
ORANGE COUNTY
2301
CAMPUS DRIVE
IRVINE,
CALIFORNIA 92664
12
MAY 1972
INDEX
SECTION
PAGE
1.0
INTRODUCTION
3
2.0
GENERAL
5
2.1
Purpose
5
2.2
Definitions
5
2.3
Existing Wall Condition
7
3.0
CONCLUSIONS
8
4.0
RECOMMENDATIONS
9
5.0
COMMENTS
10
APPENDIX A
CONTRACT SCOPE OF WORK
11
Annex A
11
Figures 1 through 9
See Link
APPENDIX B
ORIGINAL DEFINITIVE SCOPE OF
WORK AND REQUIREMENTS
12
1.0
VTN ORANGE COUNTYS SCOPE OF WORK
12
2.0
SERVICES TO BE FURNISHED BY CITY
13
3.0
SAFETY
14
3.1
General
14
3.2
Specifications
14
4.0
SPECIAL REQUIREMENTS
14
5.0
TEST METHODS AND PROCEDURES
15
6.0
TEST PANEL PROCEDURES FOR
INJECTION SUBCONTRACTOR
16
6.1
Concrete Grout and Structural Adhesive
16
6.2
FR-3 Foam and Structural Adhesive
17
SECTION
PAGE
APPENDIX C FIELD TEST PROGRAM
17
1.0
SCOPE OF WORK
17
2.0
MATERIALS
18
2.1
Non-Structural Foam
18
2.2
Structural Foam
18
2.3
FR-450 Foam
19
2.4
Structural Adhesive
19
2.5
Expansive Cement Grout
20
3.0
INJECTION PROCEDURE
20
3.1
FR-3 Foam and Structural Adhesive Injection
20
3.2
Expansive Cement Grout and Low Viscosity Structure
Adhesive Injection
24
3.3
FR-4 Foam Injection
28
3.4
FR-450 Foam Injection
30
4.0
AUTOMATIC PLACEMENT EQUIPMENT OF FOAM
ADHESIVES
30
4.1
Handling Problems of Foam Adhesives
31
4.2
Structural Adhesive Injection Equipment
32
4.3
FR-3 Foam Injection Equipment
32
4.4
FR-450 Foam Injection Equipment
33
5.0
OCCUPANT DISTURBANCE
33
5.1
Odor
33
5.2
Noise
34
5.3
Work Areas
34
6.0
(NOT USED)
7.0
STRUCTURAL EVALUATION
35
7.1
Observations
35
7.2
Quality Assurance Recommendations
36
7.3
X-Ray Inspection
36
1.0 INTRODUCTION
The
Los Angeles City Hall suffered considerable damage during the earthquake which
occurred on February 9, 1971.
Under
authorization of the Office of Emergency Preparedness, the Corps of Engineers
awarded a contract for Field Investigation to VTN Orange County.
This Contract was to investigate the manner and extent of damage to this
building. Scope of work of
investigation included the following:
(a)
Taking of high resolution photographs of all the
exterior walls of the City Hall - the majority of
which was accomplished by use of a helicopter and
specially designed long-lens camera.
(b)
Visual examination, correlation, and preparation
of tables of the extent of cracks and other damages
was accomplished through study of photographs
taken and checks against existing design drawings
of the structure.
(c)
Preparation of material lists, including replacement
cost of ceramic veneer units.
(d)
Preparation of estimates for repairing cracks and
other damaged areas.
The
field investigation effort associated with this Contract has been completed.
A Contract was also awarded to VTN Orange County for the development of
construction drawings and specifications for repair of the City Hall exterior
walls. Work is progressing on this
Contract.
During
the course of the field investigation and development of the construction
drawings for repair, it became apparent to the Corps of Engineers that
insufficient knowledge existed as to the internal composition, internal damage
of the walls, and extent of voids and cracks.
In the Investigation Report, prepared by VTN Orange County, a
recommendation was made that testing be done on certain materials which, during
the investigation phase, showed the most promise of being suitable and
acceptable in repairing the exterior walls.
The
materials and process testing recommended were developed through conferences
with manufacturers, applicators, building officials, and other contractors and
engineers.
The
materials to bond large cracks and voids which showed the most promise were
FR-3 foam, which is a two component, low unit strength adhesive produced
by Delta Plastics Company, Santa Fe Springs, California, and Expansive Cement
Grout produced by Pressure Grout Supply Company, Los Angeles, California.
In addition to these materials, injections with epoxy structural
adhesives to bond smaller cracks and voids would be required to complete the job
of bonding the walls together.
Test
locations were selected on the basis of being able to work on areas of the wall
exhibiting light, moderate and severe damage.
Further consideration was given to being able to work from roofs of the
City Hall without the necessity of using expensive scaffolding. Negotiations were undertaken with applicators, with proven
experience in handling the selected materials, to perform tests.
A proposal was then submitted to the Corps of Engineers and a Contract
subsequently awarded to VTN Orange County for the performance of the materials
and process testing program to ascertain the extent of voids, composition of the
filler material of the walls, and testing of epoxy compounds and grout material,
as detailed more fully in Appendix A
This
report concerns itself with the occurrences and developments during the
accomplishment of the test program.
2.0 GENERAL
2.1 Purpose:
The prime purpose of this program was to evaluate repair materials and
techniques. The second objective
was to determine the internal wall construction, percentage and extent of voids.
Walls are nonstructural multi-layer construction of ceramic veneer on the
exterior and brick on the inside with the area between filled with rubble
cemented together with lime mortar in a haphazard manner.
The
material quantity and procedural problems were worked out by utilizing a
systematic approach of repair and core drill, with the information gained from
the cores taken being used as a guide in the modificaion of material quantity
and placement method to be used in work on the next test panel.
As
a result of the efforts expended on the field testing of materials and
processes, VTN would be better able to develop the Construction Specifications
for the repair of the exterior surfaces.
2.2 Definitions:
2.2.1 Automatic
Injection: See In-Line System.
2.2.2 Batch mix:
This is a process of adhesive or foam mixing where the material is mixed
in
small quantities.
2.2.3 Ceramic
Veneer: The exterior layer of
the wall is made of this material. These
are hand cast,
glazed tiles produced by the Gladding-McBean Company, now known as Interpace.
2.2.4 Core Drilling:
The process of removing sections of the wall for analysis.
This process utilizes
a rotating cylindrical (6 diameter), diamond toothed, water cooled cutter
which is
anchored to the wall during the cutting process.
2.2.5 Crack-void Matrix:
The network of interconnected cracks and voids which exist in the
wall.
2.2.6 Discontinuous
voids: These are voids which exist inside the wall and are not
connected to
the matrix of cracks and voids.
2.2.7 Dynamic
Mixing Head: The mixing in this system is accomplished by a motor-driven
mixing device such as that used in the injection head for FR-450 foam.
2.2.8 Epoxy:
A family of organic chemicals frequently used as adhesives. These individual
compounds have varying properties and must be carefully matched to job
requirements.
2.2.9 Expansive
Cement Grout: On this program, this is a material having the following
formula: cement, water, Expando Group G.A. and Epoweld concrete
bonder. The latter
two products are produced by Pressure Grout Supply Company.
2.2.10
FR-3 Foam: A proprietary product produced by Delta Plastics Company.
This material is a
two component low-expansive pressure, non-objectionable odor, non-flammable, low
unit strength, foam adhesive.
2.2.11
FR-4 and FR-450 Foams: Proprietary
products produced by Delta Plastics Company.
The FR-4 was the first material produced with FR-450 being a slight
modification to provide
a longer pot life. These materials are a two component low expansive pressure,
non-objectionable odor, non-flammable, moderate unit strength, foam
adhesive.
2.2.12
In Line System: This
is a system which pumps, meters, and mixes two component
materials in a continuous manner. The
mixing may be accomplished using either a static
or a dynamic mixing system.
2.2.13
Low Viscosity - LV: A
two component structural adhesive in liquid form.
2.2.14
Machine Injection: See
In Line System.
2.2.15
Manual Injection: This
refers to the use of caulking guns for the injection of batch-mixed
FR-3 or FR-4 foams.
2.2.16
Pot Life: The period of time between the start of mixing the two
components and the
start of the curing or expansion process.
This time depends upon the formulation of the
material and temperature.
2.2.17
Pot Mix: See Batch Mix.
2.2.18
Pressure Pot: A
pressurized container used for injecting low viscosity structural
adhesives. The batch mixed material is placed in the pot which is then
pressurized forcing the premixed material into the wall.
2.2.19
Semi-Thixotropic: A
two component structural adhesive in a thin paste consistency.
2.2.20
Static Mixing Head: The
mixing in this system is accomplished by forcing the two
components through a maze such as bottle brushes.
2.2.21
Structural Adhesive: A
non-proprietary term for a material manufactured by a number of
companies. This is
normally a material in the epoxy family of chemicals available in many
viscosities and having high unit strength.
2.2.22
Thixotropic: A two
component structural adhesive in a paste consistency.
2.2.23
Void: A hollow area
in the wall apparently resulting from the original construction, which
may or may not be interconnected to other voids and cracks.
2.3 Existing Wall Condition: The wall is of a nonstructural multi-layer construction with
the ceramic veneer on the exterior, a layer of brick on the inside, and the zone
between filled with rubble, cemented together.
This rubble filled zone was not completely filled during the initial
construction of the building. The
exterior walls of the building are nonstructural walls being supported at each
floor.
The
first real opportunity to examine in detail the interior wall construction was
when injection port drilling began. At
that time it was possible to observe the varying rate of drill penetration, due
to sudden forward motion of the drill caused by voids in the wall interior.
These voids were found to be as much as 10 inches in depth.
The average thickness of the walls is 13 inches.
In most cases, there was a void immediately behind the ceramic veneer.
In
at least one occasion during inspection of the interior walls, the fireproofing
brick around the structural steel columns of the building had been placed
between the flanges without mortar and only the outside course of brick had
mortar.
The
bond of the existing mortar to brick is such that numerous cores failed at the
bond plane during the process of core drilling.
In these cases, the bond was tight enough to prevent penetration by the
adhesives, but not strong enough to withstand the forces of core drilling.
Some
cores have failed in the coring operation after injection when zones of fine
rubble and mortar were encountered. The
lime mortar does not have sufficient strength to sustain the coring forces.
Failures of this nature occurred regardless of the repair method used.
The mortar is sufficiently dense that unless injected under pressure for
an extended period of time, adhesives will not penetrate deep enough to saturate
mortar and give it strength. Cores
taken from apparently undamaged wall sections in all cases came out in more than
one piece. The bond between the
ceramic veneer and the rest of the wall seems to be minimal in the areas tested.
This condition verifies the hollow sound when the ceramic veneer on the
exterior of the building was tapped. The
areas adjacent to windows and under the window sills usually have very large
voids, apparently not having been filled during original building construction..
3.0 Conclusions
All
of the materials and procedures tested have some merit.
All of the three methods tested as described in Appendix B appear
to satisfy the structural requirements, and the exterior walls can be restored
to a pre-disaster condition by the methods tested in this program.
Data acquired indicated that the condition of the wall sections were
similar. Voids which occur in the
rubble
fill
section of the wall are frequently not filled by grout or foam material. Insofar as can be determined, these voids have only a very
small crack, if any, which connects them to the rest of the crack-void matrix,
and thus, to the drilled injection port.
A
constraining factor on the construction time required to complete the repair
work is the availability of truly qualified and conscientious personnel
experienced in handling epoxy and the specialized injection equipment.
Access for men and equipment in and around the City Hall is a problem.
Parking for Contractor vehicles is very limited and restrictive as to the
size of vehicles that can gain access to the building.
When
the cost factors are evaluated, however, the superiority of one method becomes
apparent. FR-450 Foam was developed
as the originally scheduled procedures and materials were being tested. Although the material cost of FR-450 Foam may be more than
the other materials, the cost of injection and reduced labor estimated expended
per 100 square feet of wall area indicated that this material should be utilized
in filling voids in the exterior walls.
Injection
of FR-450 foam is structurally acceptable as a method of bonding the existing
walls. Comparison of treated
samples and untreated samples together with lab testing has demonstrated that
treated walls can be restored to a condition that is structurally at least as
sound as the walls were prior to the earthquake of February 9, 1971. To insure required penetration of foam, automatic mixing and
foam injection equipment should be used which is superior to manual injection.
Repair
procedure should be restrictive to insure competitive bidding and prevent the
contractors from short-cutting application methods and material quantities.
4.0 RECOMMENDATIONS
After
completing the field effort involved with testing materials and processes, some
recommendations for the performance of the complete task have evolved. These recommendations are as follows:
(a)
The repair material should be an adhesive foam material such as FR-450,
as produced by Delta Plastics and that the foam shall be in-line mixed.
(b)
Due to the highly technical nature of the handling and injection of the
FR-450 foam, and the specialized equipment required to effect the repairs
contemplated, and because of the particular nature of this structure, a
contractors work on other structures is not sufficient proof of his
capability to effect an acceptable repair on this building.
(c)
It is recommended that the invitations to bid be given to a selected list
of contractors and those contractors be required to perform an acceptable test
panel as a condition of bid submittal. If
the test panel is unacceptable it shall be returned to an acceptable repaired
condition by the Contractor.
(d)
As an alternative, if open bidding is used, at the very minimum the
apparent low bidder shall be required to provide an acceptable test panel prior
to Contract award. If the test
panel is unacceptable, the Contractor shall forfeit one-half of his bid bond,
and another Contractor shall be selected.
(e)
Exterior cracks in ceramic veneer should be sealed with a structural
adhesive color matched to the buildings exterior prior to foam injection to bond
the ceramic veneer, internal rubble and bricks interior together.
(f)
The interior plaster on interior brick portions of exterior walls should
be removed only when necessary.
(g)
None of the damaged areas of the exterior should be removed or replaced.
The repair procedure as presently developed and recommended will restore
all of them.
(h)
The entire exterior wall area between the 5th and 26th floors should be
repaired, not just those areas which exhibit visible cracks.
(i)
The repair work should have a completion date of not more than 18 months
or less than 12 months after award of Contract.
(j)
The Contractor shall hire a moving company for all furniture moving.
(k)
The Contractor should have all leased equipment moved by the equipment
lessor.
(l)
Flammable and toxic materials should be stored in metal buildings on the
5th floor roof in locations to be designated.
These buildings shall be protected by a locked security fence to prevent
public access. The fence and the
building shall be signed in accordance with their contents. The buildings containing large quantities of flammable
materials should be further protected by an automatic fire extinguisher system
of a size and type suitable for the materials contained in the structure,
provided fire regulations of the City and State permit storage of flammable
materials on City Hall premises.
(m)
X-ray techniques should be utilized as the in-process inspection method
to determine contractor performance.
5.0 COMMENTS
Of
all the materials and processes tested, the last test panel on the 6th floor
(see Plate 5) apparently furnished the best repair for the lowest cost.
The
material FR-450 and equipment used in this final test did not exist at the
time the test program was initiated, but were developed for use on the City
Hall. It was developed and produced
by Delta Plastics Company. The
automatic injection equipment used for the test was developed and produced by
Pressure Grout Supply Company, Los Angeles, California.
When
the FR-450 foam material showed promise, VTN and its contractors and suppliers
proceeded with additional testing without requesting additional Contract
coverage at that time.
A
P P E N D I X A
Annex
A - CONTRACT SCOPE OF WORK
ANNEX
A
1. The test program of
certain areas of the City Hall as shown in Figures 1 through 9 is designed to
evaluate repair techniques under actual field conditions.
The reports prepared as the result of the tests will assist in the
preparation of project plans, specifications, estimates and bidding documents
for the repairs to the exterior surfaces of the City Hall.
The areas to be tested have been selected to furnish data on repairs for
all degrees of damage.
2. The
Contractor-Engineer shall use no less than two methods for the testing program.
3. The
Contractor-Engineer will formulate a schedule of work by areas and floors to be
submitted with his proposal.
4. The
Contractor-Engineer will be responsible for the following work to be performed
under this modification:
a.
Drawings indicating panels to be repaired, cored, and tested.
b.
specifications describing repair techniques and procedures.
c.
Specifications for coring and testing.
d.
Supervision of repairs and tests by subcontractors.
e.
Define exact test areas for each subcontractor.
f.
Define tests to be made.
g.
Define exact process for each location.
h.
Supervise subcontractor effort.
i.
Provide photographic coverage of tests and core drilling.
j.
Provide certified laboratory tests.
Figures
1 through 9 as referenced above may be found at
A
P P E N D I X B
ORIGINAL
DEFINITIVE SCOPE
OF
WORK AND REQUIREMENTS
1.0 VTN ORANGE COUNTYS SCOPE OF
WORK
The
scope of work established by the Contract is detailed in Appendix A and
includes the following:
(a)
Define exact test areas for each subcontractor.
(b)
Define tests to be made.
(c)
Define exact process for each location.
(d)
Coordinate buildings, facilities, parking availability with City
(e)
Supervise subcontractor effort.
(f)
Subcontractor effort:
(1)
Prepare areas for injection.
(2)
Inject filler material and clean area.
(3)
Inject adhesive and clean area.
(4)
Take test cores.
(5)
Close core holes.
(6)
Plug core holes.
(7)
Clean up work area and remove contractors equipment.
(g)
Correlate and report test results.
2.0 SERVICES
TO BE FURNISHED BY CITY
For
the duration of this test program on the City Hall, certain services were
assumed to be available from the City at no cost.
These services include:
(a)
Sanitary facilities
(b)
Water
(c)
110 volt electricity as required by Contractors equipment.
(d)
Parking for contractors trucks and equipment which were used for this
work.
(e)
A 4 to 6 foot wide aisle with guard as required to protect City employees
and the
general public.
(f)
Before each phase, remove furniture and furnishing from immediate area
where
work is scheduled.
(g)
After completion of each phase, return furniture to previous locations.
3.0 SAFETY
3.1 General:
Test locations have been selected to minimize staging and scaffolding.
3.2 Specifications:
The Contractors shall do their work in accordance with safety
requirements of the Los Angeles Department of Building and Safety.
The subcontractor shall also comply with applicable sections of the
following Codes: EM-385-1-1, dated
1 March 1967, General Safety Requirements, Corps of Engineers;
Construction Safety Orders, State of California, Department of Industrial
Relations, dated October 3, 1970; and Safety and Health Regulations for
Construction, Federal Register, Volume 35 No. 75, Part II, dated April 17,
1971.
The
subcontractors shall furnish all necessary safety equipment.
Scaffolding is a subcontractor responsibility. In hazardous locations such as on top of the cooling tower on
the sloping metal roof at the 26th floor, adequate protection shall be provided.
Handrails, toeboards and scaffolding shall be provided as required for
each location. All solvents and
other flammable and toxic materials must be stored in approved safety
containers.
4.0 SPECIAL
REQUIREMENTS
Due
to the nature of work to be performed under this contract, certain special
requirements exist or must be provided. These
are as follows:
(a)
The building will be occupied during the test program.
(b)
The central air-conditioning servicing the areas of work will have to be
shut down if odors or fumes prove objectionable.
(c)
Special care must be exercised to prevent damage to furniture and
equipment.
(d)
Accumulation of material and equipment beyond that required for the
immediate task will not be permitted in occupied areas of the building.
5.0 TEST METHODS AND PROCEDURES
Tests
on the job site shall be conducted to determine the following:
(a)
Extent of void filling.
(b)
Structural strength of repaired wall.
(c)
Limits of material flow in wall.
(d)
Expansive pressure of FR-3 foam.
(e)
Absorption of adhesive into wall material.
(f)
Percentage of wall void volume.
Test
cores will be removed from the test panels receiving injections and from four
selected locations in unrepaired walls. All
cores will be visually inspected to determine extent of void filling.
Selected cores will be structurally tested.
All
test data and those cores not broken during shear tests by the Testing
Laboratory will be made available for inspection by prospective bidders.
6.0 TEST PANEL PROCEDURES FOR
INJECTION SUBCONTRACTOR
The
following procedure shall be followed by the injection subcontractors. Any deviation from this procedure must be approved by VTN
Orange County prior to start of work.
6.1 Concrete
Grout and Structural Adhesive as Follows:
(a)
Protect surrounding areas and equipment from dust and debris during the
injection
port drilling process by installing temporary plastic protection floor to
ceiling.
(b)
Drill grout injection ports on approximately 2 feet on center geometric
pattern,
beginning approximately 6 above floor.
(c)
Protect building, equipment, furnishing, furniture and appurtenances from
water,
grout, and other damage.
(d)
Seal all cracks over 1/8 utilizing structural adhesive injection.
(e)
Inject cement grout, with an expansive admixture to compensate for
shrinkage,
beginning at the bottom row of holes and working upward.
(f)
All water, debris and other wastes resulting directly or indirectly from
the grouting operation
shall be cleaned up and removed by subcontractor.
(g)
Provide temporary ventilation, central air conditioning return-air
shutoff, and
other precautions, as necessary for the health, safety and comfort of the
workmen
and occupants of the building.
(h)
After the grout has taken a sufficient set (approximately three days),
the structural
adhesive shall be injected into cracks and holes from both the exterior
and interior
surface of the wall.
(i)
Remove all material and equipment from job site.
(j)
Clean area and remove all unsightly sealant material.
6.2 FR-3 Foam and Structural
Adhesive as Follows:
(a)
Protect surrounding areas and equipment from dust and debris during the
injection
port drilling process by installing a temporary plastic partition floor
to ceiling.
(b)
Drill foam injection ports approximately 2 feet on center, in a geometric
pattern
beginning approximately 6 above floor.
(c)
Protect building, equipment, furnishings, furniture and appurtenances
from
damage during the foam injection process.
(d)
Provide temporary ventilation, center air-conditioning shutoff and other
precautions as necessary for the health safety and comfort of the workmen
and
occupants of the building.
(e)
Fill all cracks over 1/8 by injecting high viscosity structural
adhesive.
(f)
Inject FR-3 foam into wall through previously drilled holes and cracks
beginning
at the bottom row of holes and working upward.
(g)
After completion of the foam injection process, all surplus materials
solvents shall
be removed from the occupied area of the building.
(h)
Inject structural adhesive from both the exterior and interior of the
wall if
required.
(i)
Remove all material and equipment from job site.
(j)
Clean area and remove all unsightly sealant material.
A
P P E N D I X C
FIELD
TEST PROGRAM
1.0 SCOPE
OF WORK
The
Scope of work, as originally envisioned, considered two materials: FR-3 foam and an expansive cement grout, used in conjunction
with a structural adhesive. During
the course of work on this program, two new materials (FR-4 and FR-450) were
developed by Delta Plastics and field tested on the Los Angeles City Hall.
Materials
in these test areas were injected by both the Hunt Process Company, Santa Fe
Springs, California (FR-3 Foam and structural adhesive) and by Warner
Engineering Services, Los Angeles, California (expansive cement grout), with
material supplied by the Delta Plastics Company, Santa Fe Springs, California.
VTN performed all management and coordination functions with regard to
this above scope effort.
2.0 MATERIALS
Materials
used in the field test program are as follows:
2.1 Non-Structural foam:
2.1.1 FR-3 Foam:
FR-3 Foam is produced by the Delta Plastics company. This material is a two component, light, non-flammable foam
with excellent adhesive properties. The
material may be either batch or in-line mixed and exhibits excellent penetration
and bond characteristics. In the
free state, the expansion ratio is approximately 20 to 1.
The unit strength, however, is quite low and makes the material
unsuitable as a structural material. This
low unit strength characteristic does not present a problem if the application
of the material is properly engineered. The
normal use of the material is to fill voids to prevent the intrusion loss of the
structural adhesive or as a fire retardant insulating material. The flame spread rating is less than 19 and smoke density of
50. This material either mixed or
in its component form, has a non-objectionable odor. This is a proprietary material and is presently in the
process of being patented by the manufacturer.
2.2 Structural
Foam:
2.2.1 FR-4 Foam:
The FR-4 foam was developed by Delta Plastics during the test program
specifically for the particular needs of this job.
When the need for a high-unit strength material to restore, at least to a
degree, the integrity of the exterior walls became apparent, discussions were
held with Delta and, as a result, this new material was developed.
It is a two component foam-in-place material, similar to the FR-3.
Its expansion ratio in the free state is approximately 6:1 with a
strength of approximately 100 psi compressive strength at maximum expansion.
It also has a non-objectionable odor.
The
fire retardance properties remain the same as the FR-3, with a flame spread of
19 and smoke density of less than 75. The
storage of these materials on the job site requires no special precautions
because both components are classified as non-flammable.
The most flammable ingredient of the A component has a flash point
in excess of 550°F.
At
this time, the FR-4 foam is a proprietary material and is in the process of
patent application by the manufacturer.
2.3 FR-450 Foam
The
FR-450 foam was developed by Delta Plastics following the testing of FR-4,
especially to have a foaming material that would perform the dual role of
filling the wall voids and providing a structural strength bond for the walls. The difference between the two materials is that the FR-450
has an extended pot life, 4-1/2 minutes at 70°F.
2.4 Structural
Adhesive
2.4.1 Delta Plastics Company:
Type TM-15-9018 A&B, pot life 10-20 minutes;
2.4.2 Delta Plastics Company:
Type AS13-9010 A&B, pot life 40-50 minutes;
2.4.3 Sika Type Colma Dur LV:
pot life 15 to 30 minutes.
2.5 Expansive
Cement Grout
Expansive
Cement Grout consists of batch mixtures of the following:
6
gallons water
1
sack (94 lbs.) regular Portland Cement
3/4
lb. Expando Grout G.A.
1/2
gallon Expoweld concrete binder
3.0 INJECTION
PROCEDURE
Injection
of materials was placed in test panels in accordance with the schedule of
events, as indicated in Table 1, herein. The
injection equipment is described in Paragraph
INJECTION PLACEMENT EQUIPMENT.
3.1 FR-3 Foam and Structural
Adhesive Injection
3.1.1 Location:
5th floor-east wing-east wall-north panel.
3.1.2 Subcontractor:
Hunt Process Company
3.1.3 Method of Repair:
The method of repair was to inject FR-3 foam followed by Delta TM-15-9018
low viscosity structural adhesive (see Table 1).
3.1.4 Injection
Port Spacing: The foam injection
port spacing varied from 3 inches to 12 inches, with the majority of this panel
being done on a 8 x 12 grid. The
holed were 12 deep, 3/8 diameter. The
adhesive was injected through open cracks.
The cracks were provided with points at 3 to 6 inch intervals, most of
which were used to determine how far the adhesive had moved.
3.1.5 Repair: the
foam injection ports were drilled in the face of the veneer and around the
window casement. There were 12
ports used on the interior in an effort to place foam in the fireproofing around
the column. Injection was performed
by batch mixing and manual injection.
The
structural adhesive was placed in open cracks on the exterior only.
The structural adhesive was injected with an in-line mixing and injection
system.
3.1.6 Description
of Holes:
FR-3
Foam Injection: Holes were drilled with a 5 inch carbide twist drill from the
exterior. A drill of this length
penetrated the ceramic veneer and the voids immediately behind the tile.
Attempts were made to inject the foam.
The result of these attempts were judged to be inconsistent and an
insufficient amount of material could be injected.
The injected material was not penetrating the crack and void matrix.
This was determined by drilling test holes to determine the extent of
foam distribution. Longer drill
bits were obtained and the wall drilled to a depth of 12 inches.
The acceptance of material in these holes was much more encouraging.
Test drilling indicated that the voids were larger immediately behind the
tile unit at the upper portion of the tile.
A total of 37 quarts of FR-3 form was placed in this panel, utilizing
batch mix and injection with caulking guns.
Coring of the wall revealed that penetration of the foam was not
sufficiently complete. The dust
from drilling had apparently effectively plugged passages and prevented the
material from entering the void matrix.
Structural
Adhesive Injection: Cracks on
the exterior of this test panel were sealed with a resinous thermosetting wax.
Injection openings were left in this seal material providing injection
ports. All cracks were injected
from the exterior through these ports since the cracks at this location were
relatively small and intrusion by the expanding foam was not a problem.
Interior plaster showing evidence of cracking was removed and the visible
cracks were injected. Approximately
one quart of material was injected from the interior.
With the plaster, it was apparent that much of the plaster was lensed
loose from the brick. The gap
behind the plaster was up to 1/8 inch. The
plaster was removed from the entire panel by simply prying it off.
Injection
ports were provided throughout the interior crack matrix and the entire interior
surface of the panel was sealed and a low viscosity adhesive injected.
Some cores again showed incomplete penetration of the smaller cracks.
In some cases what appeared to be cracks were only fractures in the
glaze; other cracks came from the
back of the ceramic veneer, but failed to penetrate the exterior and therefore,
were not injected with structural adhesive.
The same problems of window case leaking and ceramic veneer cleanup were
evidenced here, only to a greater degree.
3.1.2.8
Core Evaluation: Core
removal at this location again revealed failures in the original wall structure.
The bonds in the parent material were sufficiently tight to prevent
intrusion of the repair material, but were unable to withstand the forces of
core drilling or subsequent handling. The
foam did not fill a satisfactory percentage of the existing voids nor did the
low viscosity adhesive effectively repair enough of the cracks to be considered
as having done an adequate job of repair.
3.1.3 Location:
26th Floor-South Wall-West Panel.
3.1.3.1
Subcontractor: Hunt
Process Company.
3.1.3.2
Method of Repairs: The
method of repair was to inject FR-3 foam by manual injection, followed by Delta
TM15-9018 low and moderate viscosity structural adhesives (see Table 1).
3.1.3.3
Injection Port Spacing: FR-3
foam port spacing 15 x 15, 12 deep, structural adhesive, 8 to 10
along cracks.
3.1.3.4
Repair: Foam
injection ports were drilled in the face of the ceramic veneer and in the window
casement. Injection of foam was
accomplished using batch mixed material and manual injection methods.
Adhesive injection was done utilizing existing cracks on both the
exterior and interior upper half; the lower half was drilled on a 12 grid.
Injection in holes of this grid proved unsuccessful and then injection
was performed along the crack lines with success.
Low viscosity adhesive was injected utilizing in-line mixing and
injection equipment.
3.1.3.5
Description
of Injection Procedure.
3.1.3.5.1
FR-3 Foam Injection: Prior
to the injection of foam in the 26th floor panel, all exterior cracks were
sealed with either a paste or low viscosity adhesive, depending on the size of
the crack. Also prior to the
injection of foam in this panel, the cores were taken from the 6th floor panel. The holes for injection of foam in this panel were drilled
with a 1/2 inch roto-hammer (electric) in lieu of 3/8 inch holes drilled with a
conventional drill. This was done
for several reasons: (1) to provide
a larger injection port; and, (2) the roto-hammer does not produce the quantity
of fine dust which apparently plugs the smaller crack channels, preventing foam
entry into voids. The condition of
the wall is such that when the drill contacted brick on the inner wall, on
several occasions the brick was forced from its seal in the mortar bed.
This further verifies the minimal bond strength remaining in the mortar.
3.1.3.5.2
Structural Adhesive Injection:
The size and extent of cracking and spalling in this test panel made
structural repair efforts prior to injection of FR-3 foam mandatory.
Cracks in this panel were up to 1 inch wide causing horizontal
displacement of walls around window frames.
One of the ceramic veneer pieces was severely damaged by spalling and had
to be sealed prior to other work. In
the larger cracks, a semi-thixotropic adhesive was manually injected. Subsequent investigation revealed that this material
penetrated to a depth of 6 to 8 inches.
The
smaller cracks (under 1/16 inch) were machine injected with low viscosity
adhesive prior to foam injection. The
interior of this panel was shattered to a degree that injection ports were
placed in cracks in the upper portion of the wall and the entire face coated
with a polyester sealer. In the
lower portion of the wall, ports were placed in the open cracks and additional
ports were placed in holes drilled in the wall between cracks.
This portion of the wall was not sealed so that penetration of the
material in the wall could be observed. Injection
in all cases was started at the bottom of the panel and progressed upward.
The ports placed over the cracks accepted material much more readily than
did those placed in drilled holes. In
fact, the majority (approximately 90%) of the material injected was placed
through the ported cracks, with only an occasional drilled port accepting
adhesive. This apparently was due
to the drilled hole not reaching the crack-void matrix.
The injection done on the exterior was done through the ports left in the
crack sealant as well as some bonded in ports.
The time required to inject low viscosity adhesives into a wall structure
like that of City Hall combined with the material quantities seems to indicate
that it is not an economical method of repair.
The problem of both foam and adhesive leakage around windows became acute
at this location. The clean-up problem on panels of this damage level is
severe. Any structural adhesive
which is allowed to cure on the surface of the ceramic veneer cannot be removed
without destroying the ceramic glaze. The
residual staining problem resulting from the use of foam on the glazed surface
of the ceramic veneer must be resolved. This
will be done by changing the sealing procedure.
3.1.3.6
Core Evaluation: Evaluation
of cores removed from this test location indicated more than acceptable repair. The foam did not reach all the cracks and voids that it
should have, but this may be due to the manual injection method.
Because of the insufficient foam placement an excessive amount of low
viscosity adhesive was apparent in the cores.
Some
of these cores failed from the force of core drilling either in a bond that was
too tight to permit repair material intrusion, or in masses of fine rubble and
lime mortar.
3.2 Expansive
Cement Grout and Low Viscosity Structural Adhesive Injection
3.2.1 Location:
5th Floor-East Wing-East Wall-South Panel.
3.2.1.1
Subcontractor: Warner
Engineering services.
3.2.1.2
Method of Repair: Method
of repair was to inject expansive cement grout followed by Delta AS13-9010 low
viscosity structural adhesive (see Table 1).
3.2.1.3
Injection Port Spacing: Cement
grout was injected on a 15 x 15 grid, low viscosity adhesive was batch
injected along existing cracks at 8 to 10 inch intervals.
3.2.1.4
Repair: The cement
grout injection ports were drilled from the interior surface of the wall.
These holes were drilled 12 deep and 1-1/8 in diameter.
Low viscosity injection ports were bonded to the open crack at 3 to 4
inch intervals; however, injection was performed at 8 to 10 inch intervals with
the remaining ports used to observe the movement of the adhesive.
The low viscosity adhesive was injected using batch mixed material in a
refrigerated pressure pot.
3.2.1.5
Description
of Injection Procedure:
3.2.1.5.1
Expansive Cement Grout Injection:
The procedure for injection of expansive cement grout was aided by
information from cores removed from the 5th and 6th floor foam injection tests.
The holes for injection of cement grout were drilled with a 1-1/8 inch
pneumatic drill. Due to the
transmitted noise of such an operation, the drilling was conducted after 5:00
p.m. at the request of the City. Dust
enclosures were constructed at each location to minimize dust spread. Injection holes were drilled on approximately a 15 inch by 15
inch grid pattern to a depth of approximately 12 inches.
Prior to injection with grout, the wall panels were soaked with water.
This procedure, though is very messy, is required to prevent premature
drying of the grout and thus plugging the cracks through which it must flow.
This appears to be the messiest portion of the job due to the problems of
water control as it leaks or gushes from the wall.
The injection was started with the bottom row of holes and progressed
upward until the panel had been completely filled.
The injection continued at a port until either a pressure of 18 psig was
attained with no apparent flow, or until the grout emerged from a port at least
one row above the injection point. In
one case, grout leaked from a crack approximately 12 feet laterally from the
point of injection. Subsequent
cores indicated that the grout traveled more than 15 feet laterally at this
location.
Grout
was injected from the interior on the 5th floor, from the exterior on the 6th
floor and on the 26th floor was injected partly from each side.
There seems to be no apparent difference in performance related to
whether the injection is done from the inside or the outside.
The grout was pumped utilizing an air driven auger pump.
A gauge was located at the pump outlet and in the line near the injection
point. This gauge setup was used to determine pressure differential
and thus refusal. There was little
mess associated with this operation; this, however, is attributed to the care
exercised by the personnel engaged in the injection operation and should not be
considered as normal for a grouting operation.
3.2.1.5.2
Structural Adhesive Injection:
Plastic injection ports were bonded to cracks in the exterior and the
cracks sealed utilizing SIKA COLMA DUR GEL.
These ports were installed at 3 to 4 inch intervals along the crack with
injection occurring every third or fourth port.
The remaining ports were utilized to check on the progress of the
injection. Injection was begun at
the bottom of the cracks and progressed upward until the entire crack matrix had
been injected. The equipment utilized for the low viscosity adhesive
injection was batch mixed and injected, utilizing a refrigerated pressure pot.
3.2.1.6
Core Evaluation: The
cores removed from this panel revealed good penetration of cement grout in
general. Some of the voids in the
wall remained unfilled as did many of the cracks.
Cores failed at the bond plane of the inner brick and the rubble from the
force of core drilling. Some cores
also crumbled when large areas of mortar were encountered in the rubble section
of the wall. It was apparent that
more low viscosity adhesive was needed.
3.2.2 Location:
6th Floor-North Wing-North Wall-East Panel.
3.2.2.1
Subcontractor: Warner
Engineer Services.
3.2.2.2
Method of Repair: Method
of repair was to inject expansive cement grout followed by Delta AS13-9010
structural adhesive (See Table 1).
3.2.2.3
Injection Port Spacing: The
injection pattern for expansive cement grout was a 15 x 15 grid pattern.
The structural adhesive was injected on 8 to 10 inch intervals along the
exterior cracks and on a 10 x 10 pattern on the interior.
3.2.2.4
Repair: The cement
grout was injected from the exterior through holed drilled 12 deep.
The low viscosity adhesive was injected in ports placed on cracks on the
exterior surface. There were
visible cracks in the interior plaster when the plaster was chipped away.
Only a few hairline cracks were visible. The entire wall section was drilled 8 deep on a 10 x
10 grid and low viscosity adhesive injected.
3.2.2.5
Description
of Injection Procedure:
3.2.2.5.1
Cement Grout Injection: (See
Paragraph 3.2.1.5.1 for description of cement grout injection procedure).
3.2.2.5.2
Structural Adhesive Injection:
The cracks on the exterior of this panel were sealed with the SIKA epoxy
and plastic ports were bonded in at intervals along the surface.
Injection proceeded from the bottom up in the usual manner.
There were several cracks visible in the interior plaster, when plaster
was removed these cracks were visible in the brick. Ports were then placed over these cracks and the rest of this
wall panel was drilled on a regular (10 x 10) grid pattern, 8 deep and
ports bonded at each drilled hole. Injection
was begun at the bottom of the panel and the ports installed on cracks again
accepted the majority, approximately 90% of the injected material from the
interior. Injection pressures had
to be reduced to 20 psig from 40 psig, to prevent tearing the ports off the
interior brick. These failures
occurred in the brick, and not in the epoxy used to bond the ports down.
3.2.2.6
Core Evaluation: The
cores removed from this panel revealed good filling with the cement grout, but
some voids remained unfilled. Although
this panel was injected with low viscosity material from both the interior and
the exterior, many cracks remained unfilled.
Cores continued to fail in the same manner as on previous panels.
3.2.3 Location:
26th Floor-South Wall-East Panel.
3.2.3.1
Subcontractor: Warner
Engineering Services.
3.2.3.2
Method of Repair: The
method of repair was to inject expansive cement grout followed by Delta
AS13-9010 and SIKA COLMA DUR LV (See Tables 1 and 7).
3.2.3.3
Injection Port Spacing: Cement
grout was injected on a 15 x 15 grid.
The low viscosity adhesive was injected along existing cracks and on a
6 x 10 grid pattern.
3.2.3.4
Repair: The cement
grout on the upper half of the panel was injected through 1-1/8 inch holes
drilled 12 deep from the inside, the lower half of the panel was injected in
the same manner from the outside surface. Low
Viscosity structural adhesive was injected into ports spaced along the cracks on
the exterior wall. The interior of
the wall was divided vertically, the left half had ports placed only on the
cracks, the right half was drilled in the mortar joints on a 6 x 10 grid
with ports also bonded to the cracks. There
was no significant difference in quantities of material accepted by either half
of the wall. As in the past, 95% of
the material was injected in the ports placed over existing cracks.
3.2.3.5
Description
of Injection Procedure:
3.2.3.5.1
Cement Grout Injection: (See
Paragraph 3.2.1.5.1 for description of cement grout injection procedure).
3.2.3.5.2
Low Viscosity Structural Adhesive Injection:
The exterior of this panel exhibited severe cracking and extensive
sealing was required before injection could begin.
Ports were placed on all cracks and the cracks were filled with a
thixotropic structural adhesive. Injection
at 30 psig was begun in the normal manner from the bottom of the crack working
upward. Injection at a single port
on the exterior produced leaks over approximately a 10-square-foot area of
porosity and fine internal cracking characteristic of the existing wall
condition. Leaking was encountered
at repointed mortar joints which appeared to be tight but which leaked when
internal pressure is applied.
The
interior of the panel was divided vertically.
The left half of the panel had injection ports installed on the visible
cracks only. The right half was
drilled on a regular grid pattern with injection ports installed on all drilled
holes. Ports were also installed on
all cracks to observe material penetration.
There was very little of low viscosity structural adhesive accepted by
the drilled ports; less than 5% of the total injected.
The
amount of low viscosity structural adhesive injected was approximately the same
in both halves of the panel. By
means of these tests, the theory of being able to drill on a regular pattern and
restore the structure was disproved. Severe
leaking was again encountered around the windows.
It is apparent that the window frames will have to be sealed prior to the
injection to prevent the problems and mess associated with these leaks.
The interior surface of this panel was sealed using the low viscosity
structural adhesive and by painting it over the entire surface.
This appeared to be a very effective method of sealing.
3.2.3.6
Core Evaluation: The
cores removed from this panel revealed a more than acceptable level of repair.
The expansive cement grout did not appear to reach all the cracks and
voids that it could have. The low
viscosity structural adhesive did an excellent job of filling the crack-void
matrix. The low viscosity
structural adhesive filled large voids material which is not desirable due to
its chemical-physical properties. A
few failures occurred in the bond plane of the rubble fill to the inner brick
from the force of core drilling.
3.3 FR-4 Foam Injection:
During the course of testing work being done at the Los Angeles City
Hall, conferences were held with Delta Plastics Company regarding the
desirability of having a foaming material that would perform the dual role of
filling the wall voids and provide a structural strength bond for the walls.
A material FR-4 Foam was developed by the above company to provide a
structural strength bond for the walls. FR-4
foam was later modified for a longer pot life and called FR-450, and was tested
as hereinafter described.
3.3.1 Location:
26th Floor-South Wall-West Panel.
3.3.1.1
Subcontractor: Hunt Process Company.
3.3.1.2
Method of Repair: The
method of repair was to inject FR-4 experimental foam.
3.3.1.3
Injection Port Spacing: Approximately
10 on center in casement and small area on face of veneer.
3.3.1.4
Repair: A small area
approximately 8-square-feet, was drilled with 1/2 diameter holes 12 deep
from the exterior. The FR-4 foam
was batch mixed and manually injected.
3.3.1.5
Description of Injection Procedure:
When limited quantities of the FR-4 series material became available,
Hunt Process offered to inject this material.
This material was placed on the 26th floor; an 8-square-foot area of wall
was drilled with injection ports. In
this area, six quarts of FR-4 foam was placed.
Injection was done using manually operated caulking guns. Severe leaking of FR-4 foam occurred around the window.
3.3.1.6
Core Description: The
cores showed fair to good penetration. The
differential expansion and hardness properties were apparent in the cores. The foam in the large voids was softer than that in cracks
due to differential expansion.
3.3.2 Location:
6th Floor-North Wing-North Wall-West Panel.
3.3.2.1
Subcontractor: Hunt
Process Company.
3.3.2.2
Method of Repair: Method
of repair was to inject FR-4 foam (pilot production) material.
3.3.2.3
Injection Port Spacing: 10
x 15
3.3.2.4
Repairs: Injection
ports were drilled in the exterior face of the veneer and in the casements.
These holes were 1/2 diameter and 12 deep. Approximately 20-square-feet were included in this test area.
3.3.2.5
Description of Injection Procedure:
The test area for this material was again selected for a moderate level
of damage and accessibility. The
injection was done using batch mixed manually injected FR-4 foam.
Polyethylene sheet was used to protect the ceramic veneer from contact
with the foam and masking tape was used to seal the cracks.
3.3.2.6
Core Evaluation: The
cores removed from this location showed very good penetration of the FR-4
material. As has been the case in
other locations, some voids were unfilled, apparently these were discontinuous.
There was some evidence of uncured resins. This was determined to be the result of incomplete mixing.
3.4 FR-450 Foam Injection
3.4.1 Location:
6th Floor-South Wing.
3.4.2 Subcontractor:
Warner Engineering Services.
3.4.3 Method of Repairs:
Method of repair was to inject FR-450 machine injected foam (see Table
1).
3.4.4 Injection
Port Spacing: Ports were spaced at 15 x 15 grid and in window
casement at 8 intervals.
3.4.5 Repair:
Cracks in the face of the veneer were sealed with a structural adhesive
and the foam then injected at pressures up to 50 psig.
3.4.6 Description
of Injection Procedure: The
third test panel injected with the structural foam was performed utilizing
machine injection techniques. The
material used was from a production batch.
The machine injection equipment was developed and built by Pressure Grout
Supply Company.
There
were 14 gallons of material placed in approximately 30-square-feet of wall
surface. Three gallons of this
material was wasted in flushing the mixing head or in test samples.
Injection at a single location continued until either a pressure of 50
psig was reached or leaking on the interior of the wall was so severe as to make
further injection impracticable.
3.4.7 Core Description:
The cores removed from this test area exhibited excellent crack
penetration and void filling. Two
of the cores failed at the bond plane of rubble fill to inner brick from the
force of core drilling. One core
had to be broken to remove it as it was bonded to the steel column.
Another core was deliberately broken due to a pipe anchor attached to the
inner brick. The differential
hardness and expansion ratios were again observed in these cores.
The estimated average expansion ratio was between 2-1/3 and 3:1.
4.0 AUTOMATIC
PLACEMENT EQUIPMENT OF FOAM ADHESIVES
4.1 Handling
Problems of Foam Adhesives: The
state of the art at the time the test program began for injecting FR-3 foam was
to use a hand operated caulking gun with disposable cartridges.
At that time, the FR-450 foam had not yet been developed. There were several problems which had not been overcome that
caused this condition, and they follow:
(a)
Differential viscosities of A & B component materials.
(b)
High friction loss in lines.
(c)
Corrosiveness of B Component
(d)
Short pot life of mixed material.
(e)
Extreme adhesive properties of mixed materials.
With
the advent of the FR-450 material, the above handling problems became more
pronounced.
The
advantages of the caulking gun are obvious as follows:
(a)
Small quantity of mixed material.
(b)
Throw-away containers.
(c)
Low equipment cost.
(d)
Easy clean-up.
(e)
Highly skilled applicators are not required.
There
are certain disadvantages to this process however; they are as follows:
(a)
Injection cannot be continuous.
(b)
Mixing error probability is greater.
(c)
Injection pressure is not continuous.
(d0
Low overall injection rate.
(e)
Material may react before injection at a particular location is complete.
Automatic
equipment also has certain advantages and disadvantages.
Some advantages are as follows:
(a)
Continuous injection.
(b)
Injection at a known flow rate.
(c)
Injection at a known pressure.
(d)
Injection at a controlled pressure.
(e)
Faster injection.
(f)
Good Proportioning and mix controls.
(g)
Injection at a particular location can be completed before reaction
begins.
Some
disadvantages of this process are as follows:
(a)
High cost of equipment.
(b)
Danger of damaging equipment with both components and mixed materials.
(c)
Highly skilled operating technicians required.
4.2 Structural
Adhesive Injection Equipment: There
are two basic types of structural adhesive injection equipment in-line mixing
and batch mixing. Each of these
basic processes have advantages and disadvantages, depending on the job to be
performed and the type of material specified for injection.
During the test program, both types of equipment were utilized
successfully. After cores were
removed, there was little apparent difference in them.
The batch mix process did, in fact, place more material in the damaged
wall. Therefore, no recommendation
will be made as to a specific equipment requirement, rather the material will be
specified for specific uses and it will be the responsibility of the application
contractor to select the equipment for its proper placement.
4.3
FR-3 Foam Injection Equipment: The FR-3 foam used in the test program on the City Hall is a
product developed in late 1971, At
the time of the test program, as defined in the Scope of Work, no equipment
existed to automatically mix and inject this material.
Up to the time of this writing, approximately 500 gallons of FR-3 foam
has been placed by mixing one quart kits, poured into one quart hand caulking
guns and injected into the walls manually.
Some of the projects on which this material was used are the Ventura
County Court House and a Kraft Dairy in Iowa.
After the test program was completed, a contractor who did not perform
the previous foam injection developed equipment suitable to handle the FR-450
material.
4.4 FR-450 Automatic Injection
Equipment: An acceptable
in-line injection unit used by Warner Engineering for FR-450 foam injection was
developed for the tests. This
equipment consists of two basic components:
Model PP-MP-A pumping and metering unit; and Model MH-E-FM mixing and
injection head, manufactured by Pressure Grout Supply Company.
This will also inject FR-3 and FR-4 foam.
The
pumping and metering unit is a portable piece of equipment which is driven by
compressed air. Contained in this
unit are tanks for the A and B components and purging solvent, together with the
metering pump and their associated drive equipment.
The
mixing and injection unit is hand held against the injection port and is driven
by compressed air. The mixing is
accomplished by a dynamic heating process.
The injection unit is supplied with metered amounts of the material to be
mixed, solvents and air for purging and cleaning and compressed air for power.
The exact configuration of this equipment is proprietary.
In
its present configuration, the injection is controlled by maintaining close
communications between the operator of the pumping unit and the injection unit.
Extreme care must be taken to prevent the materials from reacting in, and
thus destroying the mixing and injection unit.
This care is necessitated by the very high cost of the mixing unit.
5.0 OCCUPANT
DISTURBANCE
The
considerations for occupant disturbance have been a factor in the selection of
materials and processes for use on this building.
The factors involved in disturbance include, but are not limited to, the
following: odor, noise, and work
area.
5.1 Odor:
Many of the structural adhesives contain materials which exude offensive
odors. Some of these odors are of
sufficient strength and character to cause discomfort or illness.
In the performance of work on this specific building, where much of the
work must be done from the interior, odor is of necessity an item to be
considered in material selection. The
group of poly-sulfide based materials are generally unacceptable because of this
characteristic. The general maximum
level of odor tolerable in this job is the SIKA COLMA-DUR LV and Delta
AS13-9010. These materials do have
a definite odor which is offensive to some people, but may be considered as a
standard for maximum odor emission.
There
were some objections to the above-specified odor level by City personnel. However, these materials have had extensive use in occupied
structures, including hospitals with a minimum of problems; therefore, they are
considered to be acceptable for use on the City Hall.
5.2 Noise:
Noise levels involved with construction efforts can reach levels which
would interfere with the work performance of City personnel and seriously affect
tape recording equipment in use during public hearings. The effect upon public hearing is of course the more
significant problem in this case.
Since
the use of pneumatic drills has been determined as necessary to provide
injection ports and this drilling produces an excessive amount of noise, the
operation of small air compressors, not to exceed 1 hp appears to be the maximum
acceptable noise level in occupied areas. There
have been some objections to noise of this level.
However, equipment of this type has been in a hospital for some months
without problems and is judged not to be excessive.
5.3 Work Area:
The work area required for restoration of the exterior walls must be kept
to a minimum. Access will be
required to the interior surfaces of al exterior walls.
Carpets where they exist, adjacent to these walls, must be removed and
protected. Nonstructural interior
partitions may have to be removed and replaced on the as-required-basis,
depending upon the extent of repair required by that particular wall segment.
It
appears at this time that a clear area of about 6 feet will be required to
perform these repairs. In addition,
access will be required from the elevators to the point of work.
Furniture
which requires movement for the test program was to have been done by the City.
This work was, in fact, done by the contractors.
The only assistance received from the City was the removal of a segment
of a nonstructural partition. All
other work, including removal and replacement of radiators was, in fact,
performed by the contractors.
7.0 STRUCTURAL
EVALUATION
7.1 Observations:
Foam injection has been evaluated by:
7.1.1 Observation
and testing of made up samples
7.1.2 Examination
of core samples removed from walls, both prior to and subsequent to foam
injection observation of field procedures.
7.1.3 Physical
testing of core samples and evaluation of test results.
Samples were made up with used clay brick and FR-450 foam.
One type of sample was made by bonding the faces of two bricks with foam,
while another type was made by stacking alternately faced brick in a cardboard
box and pouring the foam into the container, allowing the natural expansion of
the foam to fill the voids. These
samples were then tested to destruction.
7.1.4 Field Methods of Foam Injection are discussed
elsewhere in this report; however, two foam injection systems were observed:
manual injections, and injection utilizing automatic mixing and injection
equipment. Subsequent to injection,
cores were removed from both treated and untreated wall areas for laboratory
testing. Samples tested were
subjected to shearing and compression type loads.
In each case they were tested to destruction.
Shear tests were made utilizing a specially manufactured collar, which
retained one-half of the sample while permitting the other half to slide at
failure in such a manner that a shear mode was simulated.
compression samples were capped with sulphur prior to testing.
All testing was done utilizing the Tinius Olsen testing machine,
the Baldwin testing machine. Both
shear and compression test results were wide ranging, and as such, little weight
should be ascribed to actual numerical values obtained.
Also, it was not possible to obtain testable samples from untreated
wall areas due to crumbling of the material under the action of the coring
machine and the general condition of the wall.
Samples of treated wall varied in condition from poor to excellent,
In some cases, the samples were composed of approximately 50 percent
structural adhesive. Numerical test
results do have some correlation to the individual samples tested to the degree
that those cores that had good structural adhesive penetration generally tested
higher than cores that had poor penetration.
As such, numerical values appear to be dependent on degree of
penetration, condition of original brick, and condition and quality of original
mortar. Failure of samples in every
case occurred predominantly in original material.
7.2 Quality Assurance
Recommendations: The normal
quality control procedure for structural adhesive injection is to take a core at
specified frequencies, based on length of cracking.
This method does not appear suitable for the specific problems associated
with the Los Angeles city Hall structure. In
place of the normal frequency of core drilling, a sampling plan is proposed:
(a) Cores shall be drilled per
1,000 square feet of exterior wall surface.
These cores shall be located in an area less than 5 percent of the total,
selected at random after completion of the area.
(b) If two of the three cores
taken are not properly repaired, then three more cores shall be taken.
These additional cores shall be taken at the expense of the Contractor.
(c) If two of the three cores
taken on the second sample are not properly repaired, then the entire area
involved in this inspection shall be reworked by the Contractor at no cost to
the Government.
7.3 X-Ray Inspection:
The possibility of utilizing X-Ray techniques to determine voids in the
unrepaired wall sections and to determine the extent of injection has been
discussed with engineers and contractors in the past with little, if any, hope
for success. Twining Laboratories
expressed a desire to attempt X-Ray evaluations. Initial testing was performed on cores removed from the
structure. The results of these
tests were sufficiently encouraging to warrant full scale testing on the subject
building.
On
Friday, March 24, 1972, full scale tests were conducted on wall panels of the
City Hall Building. Photos were
taken of both unrepaired and repaired segments of the wall.
The comparison of the photos of the unrepaired and repaired wall segments
showed a marked difference resulting from the intrusion of the foam material.
The
X-Ray process seems to be a more economical method than that of removing and
replacing cores. If disputes
occurred over X-Ray interpretation, cores could still be taken as a final check.