Department
of Civil & Geomatics Engineering & Construction

Prepared
by:
A.
El-Zeiny, Ph.D., P.E.
and
J.
Larralde, Ph.D., P.E.
August
2000
Abstract
A
pioneer technique to repair un-reinforced brick walls cracked during past
seismic events, or to retrofit existing brick walls to meet the current code
requirements is subjected to experimental investigation. Such walls are very
common in historical buildings. The walls are injected by expansive epoxy, known
as Bisfoam-3.
After the material is shot into walls, it expands, bonds and hardens. This
injection technique does not affect the appearance of these historical walls and
consequently it preserves their historical value. The investigation consists of
testing the seismic performance and ductility of the plain brick walls first.
Then, those broken walls are repaired using the foam and tested. In addition,
another set of walls that has not been broken first are strengthened with foam
and tested. Performance of all walls is studied and compared to prove the
effectiveness of the foam material in the retrofitting and repairing of brick
walls.
1.
Introduction
Epoxy
materials have been used in the past in the preservation of old masonry systems
including brick masonry buildings. For the most part, the traditional technique
consists of applying epoxy to seal the porosity of the masonry units or to make
the masonry more watertight and therefore more resistant to the effects of the
environment. To a lesser extent epoxy has been used to restore the strength of
masonry systems. In the project reported herein, a new type of epoxy formulation
produced by Delta Plastics Company, called Bisfoam-3, was tested to determine
its potential for structural retrofitting and strengthening of existing brick
masonry buildings.
The
Delta Plastics Co. Bisfoam-3 is simple to explain. Bisfoam-3 is a monolithic
complex composite. This composite material, when injected into a void area
within the walls of buildings increases the ductility, damping and strength of
these walls. Without this material inside the wall, catastrophic failure is the
norm in case of major seismic events.
This
report presents the results from the laboratory testing of four brick wall in
the structural lab of California State University, Fresno. The size of walls is
10 ft by 10 ft by 10 inch thickness with 2 inches void in between and they are
fabricated using aged brick and masonry mortar to simulate the conditions
existing in old brick buildings. Two walls were loaded directly as plain,
un-reinforced brick wall and results were obtained. The other two walls,
identical to the first ones, were first injected with the foam material, allowed
to cure for seven days and then tested under similar support and loading
conditions. After the plain walls were loaded beyond their full cracked state,
they were also repaired with the foam material and re-tested. The results of the
tests demonstrate the feasibility and potential of the technique to restore the
type of structures and demonstrate the potential for earthquake retrofitting or
strengthening.
2.
Historical Background
A considerable number of un-reinforced brick masonry buildings were built throughout the world in the past and now they constitute an irreplaceable historical asset for civilization. These structures were built following construction techniques different from the current ones and were built to minimal or no construction codes. In the west coast of the United States, a good number of these types of buildings were built during the 18th and 19th centuries following the techniques of the time. Coincidentally, the great majority of these structures are on, or near zones of high seismic activity. That many have survived the numerous earthquakes since their construction is a proof of the quality of workmanship with which they were built. However, so many of these historical buildings are of incalculable aesthetic and historical value and it is not appropriate to leave their preservation dependant to their good luck. Various strengthening and retrofitting techniques have been used through the years, including more recently the used of high strength fiber composite materials (Hamid et al. 1993, Bhende and Ovadia 1994, Keheo 1996, Ehsani and Saadatmsnesh 1996, Velazquez-Dimas et al. 1999). Also, epoxy injection and consolidation started to be used in the 1960’s in Poland Domaslowsy and Strzelczyk 1986) and 1970’s in the United States (Gauri and Madiraju 1978). Although the main focus of epoxy repair or conservation has been geared towards the sealing of the porosity or cracks in stone, brick, and mortar materials, to protect them against the weather effects, there has always been a desired to provide also structural enhancing with the epoxy.
In 1971, the technology of FR-4 was developed specifically for the rehabilitation of the Los Angeles City Hall building, see Figure 1 , which was severely damaged in the 1971 San Fernando earthquake. The FR-4 product would be chemically irreproducible after 1976 due to the use of Freon as the foaming agent. This technology is now back into chemical production and renamed to Bisfoam-3. The Delta Plastics Co. Bisfoam-3 is now foamed or “blown” by the formation of CO2 instead of Freon, which is a non-regulated method of chemical expansion.
Bisfoam-3 is a functional equivalent to the time tested, in-place exposures of Whittier, Northridge, and all other ground movements as reported by Cal Tech. After better than 30 years of on the job service, the epoxy foam is still in pristine condition and is ever vigilant for the next ground movement. The Delta FR-4 application at the Los Angeles City Hall was accomplished by VTN of Orange County with the assistance of the Army Corps of Engineers, the Office of Emergency Preparedness, better known as FEMA, and the approval of the Los Angeles building department. The Los Angeles City Hall report (Galletti, 1972) outlines extensively the application, building condition, and other methods considered. The 19th method tested was the Delta foam developed by Delta Plastics. The technologies obtained from the restoration of the Los Angeles City Hall along with their engineering and architectural skills made VTN of Orange County a natural choice for the State Capitol building restoration project. The Delta Bisfoam-3, when compared to other types of restoration methods including base isolation technology, is both cost effective and time tested. The Bisfoam-3 epoxy has also been utilized in three applications other than the Los Angeles City Hall, which are Ventura City Hall, Alameda City Hall, and Mayflower Presbyterian Church in Pacific Grove, California in 1999. During three of these projects, the application of the Bisfoam-3 was straightforward. The Mayflower Presbyterian Church application was unique. The church is a single load-bearing wall structure. The approximately 1-2 inch of void area was created many years ago with the use of common plywood and drywall. This application, although altering the interior face of the wall, shows that seismic upgrading can be accomplished with the use of a manufactured confinement area. The application was accepted and now church services have resumed. Void areas will vary and may also be rubble filled. Rubble filled walls may pose the need for extra attention. The Los Angeles City Hall was a rubble-fill-wall application.
3.
Construction Procedure
Typical
brick walls of historical buildings are made of two layers of brick with 2
inches gap in between to provide insulation. Holes are drilled in the outside
bricklayer to reach to the 2-inch gap to pump the expansive epoxy in a liquid
form. The holes are drilled in a diamond shape distribution as shown in Figure
2 with 2 feet spacing on center. Expansive epoxy is pumped at
about 70°F
temperature in the lowest row of holes till it leaks out from neighbor holes
showing that this particular section of the wall is full of epoxy as shown in Figure
3 . Then after few minutes, the foam starts to expand and hardens.
The estimated expansion ratio for all walls in this test was 1:3.8. The
necessary time for the foam to cure is seven days. The method can also be
implemented for brick walls with single layer of brick. The
approximately 2 inch of void area can be created by the use of common plywood
and drywall.
The
brick that was used to build the four walls used as test specimens was obtained
from the 1900 vintage era. It came from demolished historical buildings. It
should be noted that the mortar used to build the walls for this test was
according to ASTM standards. In the actual historical buildings, the mortar has
deteriorated to the level that it can be easily removed by a pocketknife. In
addition, due to the lack of quality control at the time of construction of
historical buildings, the variability of the strength of both the brick and the
mortar is high. The main concept in this test is to test the plain walls without
any foam and establish this as a reference line against which repaired and
retrofitted walls are compared. This will clearly point out the improved
mechanical properties due to the use of foam. Another immediate advantage of
using the foam is that it substitutes for the deteriorated mortar joints. It
makes the loose brick wall more monolithic and increases its integrity. In
addition, the ductile foam substitutes for the brittle mortar making the wall
able to produce much more ductile response in case of seismic ground motions.
4.
Test Set-Up
Four
walls are built in the structural testing lab at California State University,
Fresno. Two walls will be subjected to out-of-plane force and the other two will
be subjected to in-plane force, as shown in Figure 4
and Figure
5 . In case of the out-of-plane walls, the axial loading is
limited to the own weight of the concrete header beam on the top, the weight of
the two steel beams in the middle and the additional weight due to the own
weight of the actuator. This adds 3500 lb of additional weight to the wall. This
represents the worst-case scenario because increasing the axial load is expected
to increase the flexural capacity of the wall. This is attributed to the fact
that the wall is much stronger in compression than in tension. The axial load
acts like a pre-stressing load where it increases the initial axial compression
stress on the wall causing the tension crack to develop at a much higher load.
In
the case of in-plane walls, the axial load in the test of the first wall was
made of the weight of the concrete header beam and the own weight of the
actuator, which is 1900 lb. Such axial load represents the worst-case scenario
where a brick wall is supporting one light roof. In the test of the second wall,
the axial load was increased by adding two concrete block carried by steel beam
from the bottom as shown in Figure
21 . The axial load in this case adds up to 11,000 lb. The
objective of this is to explore the change in wall mechanical properties in case
of the wall supporting heavier roofs or multiple floors.
5.
Presentation of Results
5.1
Out
of Plane Wall without Foam
The
test was a cyclic displacement control test. The period of one cycle is 10
seconds. The amplitude of the first cycle was 0.01 inches and the increment was
0.01 inch per cycle.
The
load deflection curve shown in Figure
6 shows typical hysteresis loops with expected stiffness
degradation. The ultimate capacity of the brick wall is 3000 lbs. The wall
starts cracking at about 2000 lbs and 0.1-inch deflection. The wall becomes
fully cracked at 0.15-inch deflection. Increasing the displacement more than
0.15 inch will cause the wall to deform in a rocking mode where the cracks will
simply open and close without providing any resistance. As the deflection
started to approach a value of 0.3 inch, the wall starts to show signs of
collapsing. The test was then stopped to prevent the wall from going into
catastrophic failure where the bottom of the brick wall would slide out of the
plane of the wall and the entire wall will then collapse. It was intended from
the beginning to just crack the wall to make the idea of repairing the wall and
retesting it possible. Two horizontal cracked sections were observed: one right
above the horizontal steel beam connected to the actuator and the other was at
the bottom of the wall near the foundation. These two cracks separate the wall
into three separate pieces; one below the bottom crack, the second is between
the bottom and middle cracks and the third is above the middle crack. The wall
may then slide out of its plane along these two cracks causing a catastrophic
brittle failure.
5.2
Out
of Plane Wall Repaired with Foam
The
test was a cyclic displacement control test. The period of one cycle was 10
seconds. The amplitude of the first cycle was 0.02 inches and the increment was
0.02 inch per cycle. This test was done in two phases. In phase I, the wall was
pushed to a total deflection of one inch. In phase II, the wall was pushed to
the full stroke range of actuator, which is plus or minus five inches. Figure
7 and Figure
8 show hysteresis
loops
for both phases. The wall has reached to a deflection of five inches in both
directions without catastrophic failure as shown in Figure
9 . Two
horizontal cracked sections were observed: one right above the horizontal steel
beam connected to the actuator and the other was at the bottom of the wall near
the foundation. At each horizontally cracked section, a
plastic hinge was formed with a length equal to the length of the wall. Such
ductile plastic hinges were not possible to form without the foam. It is
observed that the strength of the wall increased by 24% due to the injection of
the foam. This indicates that the injection of the foam not only restored the
strength of the cracked wall by sealing all previous cracks, but also increased
the strength by 24%. Add to that the added ductility and damping due to the
formation of the plastic hinges.
5.3
Out
of Plane Wall Retrofitted with Foam
The
test was a cyclic displacement control test. The period of one cycle was 10
seconds. The amplitude of the first cycle was 0.01 inches and the increment was
0.01 inch per cycle up to 1 inch of total displacement. After that, the
increment was 0.05 inches per cycle. Figure
10 shows typical
hysteresis loops with expected stiffness degradation. The ultimate capacity of
the retrofitted wall is 4200 lbs. The wall cracked at a section right above the
horizontal steel beam connected to the actuator. After cracking, the walls
started to deform in a rocking mode where the cracks will simply open and close
as shown in Figure
11 . This rocking mechanism was similar to the mechanism developed
in the repaired walls.
5.4
Comparison
of Results from Foamed Walls with Results from Plain Brick Wall
Figure
7 shows that the ultimate strength of the repaired wall increased
to 4500 lbs, which is 1500 lbs more than the plain brick wall. Figure
8 shows that the wall is very ductile because it took a deflection
up to five inches without collapsing. This ductility is attributed to the
formation of the plastic hinges in the middle and at the bottom of the wall. One
may argue that the wall was prevented from catastrophic failure because the
actuator laterally braced it. Such an argument is not valid because the load did
not reverse sign. In other words, if the wall is prevented from collapsing by
the actuator, then the force in the actuator will be tension instead of
compression in one direction, or compression instead of tension in the other.
But the shown load deflection curve in Figure
8 is showing that up to five inches of deflection, the actuator
had to push/pull the wall with a force of 2100 lbs to produce a five inch
deflection, i.e. the wall still has a resistance of 2100 lbs at five inches of
deflection. If the applied actuator force of 2100 lbs is removed, then the wall
will return to a position close to the at rest position. This magnitude of
deflection is very ample to prove a very ductile behavior of the originally very
brittle brick wall keeping in mind that the maximum deflection that can be
produced by the actuator used is plus or minus five inches, i.e. the test was
stopped at 5 inches because of the limitations of the testing equipment not
because of the wall reaching its ultimate capacity. It was not possible to see
such ductile plastic hinges in the wall without the foam. A catastrophic failure
would have taken place because the portion of the wall above any of the two
horizontal cracks may slide out of the plane of the wall causing the wall to
suddenly loose the ability of carrying vertical loads, which means sudden fall
down of the floors and/or roofs supported by the wall.
Comparing
the load-deflection curve of the retrofitted wall to the repaired wall shows
that the load required to form the plastic hinge increases by 20%. Another
observation in the retrofitted wall is the sudden drop of load after the
formation of the plastic hinge. This sudden drop of load is attributed to the
fact that cracking of the brick mortar is brittle failure. In the repaired wall,
this crack has already taken place when the wall was initially cracked before
the injection of the foam. This explains why we see gradual drop of load with
the increase of deflection beyond the formation of the plastic hinges in the
repaired wall while a sudden drop of load is observed in the retrofitted wall
that has not been cracked before.
5.5
In
plane Wall without Foam
The
test was a cyclic displacement control test. The period of one cycle was 10
seconds. The amplitude of the first cycle was 0.005 inches and the increment was
0.005 inch per cycle. The
vertical load applied on the top of the wall was not symmetric because of the
weight of the actuator. Another reason is the uplift of the actuator when the
wall is pushed versus no uplift when the wall is pulled. The resistance of the
actuator to uplifting is high when the wall is pushed. This mechanism yielded a
non-symmetrical hysteresis
loops. It
was decided to consider only the pulling side of the hysteresis loops because
the actuator does not uplift in this case. Figure
12 shows
only the pulling side of the hysteresis loops. The pushing side is omitted
because it does
not
represent the pure strength of the wall. The wall failed in tension at
horizontal mortar joints near the bottom of the wall as shown in Figure
16 . Horizontal mortar joints near the bottom of the wall have
cracked and the portion of the wall above these joints started to uplift and
rock in a rigid body motion. The ultimate capacity of the wall was 3860 lb.
There were no signs of shear failure.
5.6
In
plane Wall Repaired with Foam
The
wall that was broken previously without foam was repaired by injecting the foam.
The wall is then left for several weeks. After that, the wall is tested in two
phases. The first phase was a monotonic test where the wall was pulled to a
deflection of 0.25 inch. As shown in Figure
13 , the capacity of the wall has increased from 3860 to 5750 lb,
i.e. 49%, as a result of the foam. This relatively large increase in capacity is
attributed to the fact that the failure section after injecting the foam has
shifted 22 inches towards the bottom of the wall as shown in Figure
16 . This increased the arm of the bending moment inducing the
failure as well as increased the size of the portion of the wall above the
failure section that has to uplift before the failure can take place. Both
factors, the arm of the bending moment and the weight of the uplifted portion of
the wall, contribute to the resisting moment.
The
second phase was a cyclic displacement control test. The period of one cycle was
10 seconds. The amplitude of the first cycle was 0.02 inches and the increment
was 0.02 inch per cycle. This test was done after the wall has developed the
failure crack in the monotonic test without any repair. Due to non-symmetrical
loading conditions, only the pulling side of the hysteresis loops is shown in Figure
14 .
Figure
15 and Figure
16 show the wall at failure. It was observed that the cracks that
opened during the testing of the un-injected wall did close as a result of the
foam. In addition, the foam helped in preserving the integrity of the wall by
helping the mortar joints in transferring the loads between bricks. Due to the
brittle nature of the mortar material, mortar fails first. The foam material is
ductile and allows much more deformation before it fails. This allows more
energy absorption and dissipation in seismic events. It also increases the
damping of the wall, which leads to better seismic performance. After the wall failed
in tension cracks at horizontal mortar joints, the part of the wall above
cracked mortar joint started to rock in a rigid body motion. There were no signs
of shear failure.
5.7
In
plane Wall Repaired with Foam and Anchored with Fiberglass
Figure
16 show the failure cracks before and after repairing with foam.
The foam sealed the original failure cracks and the wall cracked at a section
near the foundation where there is little amount or no foam. As a result, it was
decided to repair the wall again for the second time using fiberglass and epoxy.
The fiberglass was glued to both wall and foundation to provide anchorage
between the wall and its foundation, and to cover the area at the bottom of the
wall where there is little amount or no foam. As shown in Figure
17 and Figure
18 , the fiberglass anchorage was installed on one side of the
wall only to simulate the real life conditions where only one side of the wall
is accessible. The fiberglass has also covered the second failure crack produced
due to the testing of the repaired wall.
The
wall was then subjected to a cyclic displacement control test that ranges
from zero to maximum value. During one cycle, the wall is pulled from the
neutral position to a maximum value and then returned back to the neutral
position. The wall is not pushed due to the unsymmetrical loading conditions
explained before. The period of one cycle was 10 seconds. The amplitude of the
first cycle was 0.02 inches and the increment was 0.02 inch per cycle up to 1
inch of total displacement. After that, the increment was 0.1 inch per cycle. Figure
19 shows the hysteresis
loops of the wall when subjected to such cyclic excitations. It was
observed that the wall has cracked at a horizontal mortar joint section right
above the fiberglass as shown in Figure
20 , and the resistance of the wall jumped from 5800 lb to 7000 lb, i.e.
21%. This increase is attributed to the fact that the fiberglass prevented
failure at the bottom of the wall where is little or no foam and forced the
failure to take place in an area of the wall rich with foaming material.
5.8
In-plane
Retrofitted Wall with Foam and Anchored to Foundation
The
axial load in the test of the first in-plane wall was made of the weight of the
concrete header beam and the own weight of the actuator, which is 190 plf or 2
psi. Such axial load represents the worst-case scenario where a brick wall is
supporting one light roof. In the test of the second wall, the axial load was
increased by adding two concrete blocks carried by steel beam from the bottom as
shown in Figure
21 . The axial load in this case adds up to 1100 plf or 11.5 psi. The
objective of this is to explore the change in wall mechanical properties in case
of the wall supporting heavier roofs or multiple floors.
5.8.1
Wall is Anchored with Fiberglass Only
The
test was a cyclic displacement control test
that ranges from zero to maximum value. During one cycle, the wall is pulled
from the neutral position to a maximum value and then returned back to the
neutral position.
The period of one cycle was 20 seconds. The amplitude of the first cycle was
0.01 inches and the increment was 0.01 inch per cycle. The period was increased
to 20 seconds instead of 10 seconds to prevent the oscillations of weights
hanged from the top of the wall. The test stopped as soon as the tension crack
shown in Figure
23 was observed. The load deflection curve shown in Figure
22 indicates that the test was stopped at a deflection of 0.31
inch. It was possible to continue the test beyond this point; however, it was
decided to stop the test to install a chain that anchors the wall to the
foundation to prevent the tension crack from further progressing.
5.8.2
Wall is Anchored with Fiberglass and Steel Chain
The
test was a cyclic displacement control test
that ranges from zero to maximum value. During one cycle, the wall is pulled
from the neutral position to a maximum value and then returned back to the
neutral position.
The period of one cycle was 10 seconds. The period was decreased back to 10
seconds because it was found that 10 seconds period is long enough to prevent
significant oscillation of the concrete blocks hanging from the wall. The
amplitude of the first cycle was 0.05 inches and the increment was 0.05 inch per
cycle. The chain was installed as shown in Figure
24 to prevent the tension crack developed from progressing and to
force shear failure mechanism. The extra axial load produced by the stretching
of the chain simulates the case of a load-bearing wall carrying several floors.
In this case, tension cracks are not possible due to the heavy axial load due to
the dead and live loads from the supported floors. The chain did not totally
prevent the wall from uplifting because the chain was not pre-stressed. The wall
had to uplift for some distance to stretch the chain and produce the desired
axial load. Figure
25 shows the hysteresis loops until failure of the connection
between the wall and foundation. The entire wall has slide for a distance of two
inches on its foundation and the foundation itself has cracked as shown in Figure
26 . The wall itself showed no signs of any additional failure
than the tension crack produced in the previous test. Before the wall slides,
the fiberglass pulled out of foundation due to the uplift of the wall. Such a
failure is not expected in real life applications because dead and live loads
will apply heavy compression stress on the wall that may reach up to 40 psi or
3850 plf. Such heavy axial load will not make uplifting of the shear wall
possible. The real life failure mechanism of brick walls under heavy axial loads
is expected to be stair-steps diagonal crack in mortar joints due to the effect
of diagonal tension.
Figure
26 also shows a piece of fiberglass pulled out of the wall. It is
clear from the picture that the boding strength between the fiberglass and brick
wall due to gluing epoxy exceeded the strength of the brick itself. This
resulted in a thin layer of brick pulling out of the wall and remaining with the
fiberglass. This leads to the conclusion that using such an epoxy in gluing the
fiberglass to the brick wall is adequate because it provides bonding resistance,
which is more than the shear resistance of the brick itself.
5.8.3
Wall is Laterally Supported by Steel Strut and Anchored with Fiberglass and
Steel Chain
The
same wall was repaired and tested for the third time. This time, a lateral steel
strut was installed at mid height of the wall as shown in Figure
27 to provide lateral support and to prevent the wall from going
into further sliding when pulled. Sliding failure is not expected for such walls
under heavy axial loadings. The effective loaded portion of the wall is the top
half of the wall, which simulates a wall of aspect ratio of 2:1. That portion of
the wall was free of any cracks or signs of failure due to the previous two
tests. The wall was then subjected to a cyclic displacement control test
that ranges from zero to maximum value. During one cycle, the wall is pulled
from the neutral position to a maximum value and then returned back to the
neutral position.
The period of one cycle was 10 seconds. The amplitude of the first cycle was
0.05 inches and the increment was 0.05 inch per cycle. The chain was kept in
place to prevent the wall from uplifting and to provide extra axial loading when
stretched. First, a curved tension crack was formed as shown in Figure
29 to allow the wall to uplift a little bit to stretch the chain.
Such uplifting was necessary for the chain to develop enough axial loading to
produce the desired failure mechanism. Then the stair-steps diagonal-tension
crack was developed as expected. This failure mechanism is expected in case of
brick load-bearing wall supporting heavy axial loads. Figure
28 shows the hysteresis loops until the formation of the
stair-steps diagonal crack.
6.
Physical Properties of Bisfoam-3
6.1
Fire
Resistance
The
Delta Epiceramictm Bisfoam-3 A&B is a two component, fast foaming
system. The system cures to a low density, rigid closed cell foam with
outstanding non-burning properties along with excellent low expansion pressure
properties. The tough, rigid, ductile polymer has a flame spread of less than 19
as well as a smoke density of less than 75 and is ablative in nature. The cured
foam, when exposed to open flame, will char with little damage to or deformation
of the foam structure. The smoke emitted contains decomposition products of
carbon, hydrogen, water, and traces of chlorine and fluorine. In addition there
is a low odor quality. The Bisfoam-3 A&B fire resistance testing is as
follows: MIL-I-16923D, ASTM D568, ASTM D635, ASTM D757, ASTM D1433; passes all
tests. The versatility of the epoxy foam polymer allows for large mass foaming
and its ease of handling allows for many types of molding applications.
In addition to its fire retardant properties, several other features are displayed by both the uncured and cured foam:
1.
The epoxy foam is designed for in-head mixing equipment where fixed
ratios are present. This provides the applicator with the ability to place large
amounts of product very quickly and reduces labor and material waste.
2.
DELTA BISFOAM-3 A&B can be sprayed with currently available foam
spray equipment. Chopped fiberglass can be sprayed along with the foam to obtain
a glass-reinforced foam.
3.
The mixed system foams as a fast, soft rising foam with low internal
foaming pressures allowing the foam to be contained into specific areas without
excessive pressure being generated. Lab tests indicate a maximum of 2 psi
foaming pressure.
4.
When the foaming action is complete, the foam is tack free. The elapsed
time from start of mixing to tack free is less than 3 minutes at temperatures
between 78°F and 82°F in masses of no less than 20 grams.
5.
The cured foam has excellent adhesion to a wide variety of materials such
as brick and other masonry products as well as lead, zinc, copper, aluminum,
iron, tin, some types of polyethylene, polypropylene, kynar, epoxy, polyesters,
tile, terra cotta, and marble. The foam also bonds to itself.
6.
The cured foam has excellent thermal stability when exposed to open flame
and excellent dimensional stability when tested for 160 hours at 300°F
7.
The thermal insulating qualities of the cured foam at a 4 pound density
show a K factor of .19 BTU/hr/ft²/°F/in.
6.2
Handling
Characteristic
Resin
(Part A)
100 Parts by Weight
Hardener
(Part B)
10 Parts by Weight
It
should be noted that both Part A and Part B of this foam system should be
stirred thoroughly prior to using to ensure that no separation of ingredients
has occurred. The Part A of the foam system should be preheated to a temperature
between 78°F and 82°F prior to in-head mixing and maintained at such
temperature during injection. The resulting foam density will be a function of
the temperature and the mass of the material being foamed.
The
foaming action accomplished in a free foaming, unrestricted area will develop a
2.5 to 4 pound density or up to a 10 to1 volume expansion ratio. The foaming
action accomplished in a confined will result in an end-foamed product with a
higher density. It should be noted that Protective clothing and cleanliness
should always be used when working with epoxy resins and hardeners. If skin
contact is made, wash the area with soap and water. If the materials get into
the eyes, rinse with quantities of water and consult a physician. Use epoxy
resins and hardeners only in well ventilated areas and avoid breathing of
vapors.
6.3
Curing
Characteristic
Property
Description
Approximate Time
Pot
Life, 110 grams, 78-82°F
45-75 seconds
Cream
Time
1-2 minutes
Foaming
Complete
3 minutes
Tack
Free
3.25 minutes
Initial
Cure
45 minutes
Full
Cure
4 days
6.4
Suggested
Storage Procedure
The foam as supplied should be stored at temperatures below 80°F. The shelf life of unopened containers will be a minimum of 1 year. However, separation of the ingredients may occur over a long period of storage.
6.5
Availability
of Material
The
DELTA EPICERAMICtm BISFOAM-3 A&B is available in the following
standard kit sizes where the resin (Part A) is supplied in 5-gallon pails,
1-gallon cans, and 1-quart cans with the proper amount of hardener packaged in
an appropriately sized container. The material is packaged at a ratio of 100
parts by weight of resin (Part A) to 10 parts by weight of hardener (Part B).
5-Gallon
Kit
1-Gallon Kit
1-Quart Kit
Part
A, Weight 40 lbs.
8
lbs.
2
lbs.
Part
B, Weight
4 lbs.
.8 lbs.
. 2 lbs.
7.
Ductility of Walls
The
seismic design provision of the UBC 1997 and previous editions require the
designer to divide the seismic force by a ductility coefficient “R” when
calculating the total design base shear for the building. The “R”
coefficient for various building systems can be obtained from tables 16-N and
16-P in the UBC 1997. UBC does not provide a value for the system of brick walls
injected with foam. However, section 1629.9.2 allows the establishment of
“R” value for unlisted systems using cyclic test data and analysis. Our
objective in this section is to analyze the test data to obtain a value for the
“R” coefficient.
The
ductility of the structural element is generally defined as the member’s
ability to undergo deformations without a substantial reduction in its load
resisting capacity. The ductility can be defined either by the curvature
ductility factor or by the displacement ductility factor. The curvature
ductility factor is the ratio of the section curvature at ultimate strength to
the curvature at the beginning of the nonlinear plastic behavior. The
displacement ductility factor is the ratio between the maximum horizontal
displacement of the wall at ultimate strength and the maximum horizontal
displacement at the beginning of the nonlinear plastic behavior. The second
definition is adapted herein. In order to apply this definition, one must
determine at what point should we consider the wall at the beginning of the
nonlinear plastic behavior and at what point should we consider the wall at its
ultimate strength. The following procedure is adapted to determine the point of
the beginning of the nonlinear plastic behavior; first, the envelop of the load
deflection hysteresis loops is drawn. This envelope represents the traditional
load-deflection curve obtained in case of a monotonic test. The slope of this
curve at any point represents the stiffness of the wall at that point. The
beginning of the nonlinear plastic behavior is considered at the point where
there is a significant change in the slope of the load-deflection curve. A
different approach is used to determine the point of ultimate strength. In the
case of out-of-plane walls, the ultimate strength is considered to be the point
at which the line of action of the supported vertical load passes by the
overturning point as shown in Figure
30 . If the deflection of the wall is allowed to go beyond this
point, then the supported vertical load is going to contribute to the
overturning moment instead of the stabilizing moment and the wall may go to the
instability condition. Therefore, this constitutes the point of ultimate
strength, which is equal to the smaller of the thickness of the two layers w1
or w3. In this test, w1=w3=5 inches and w2=2
inches. Based on these numbers and definitions, the ductility factor is
estimated to be ten. Accounting for a factor of safety of two, it is recommended
to use an R factor of five.
In
the case of in-plane-wall, the point of ultimate strength is observed during the
test. It is defined as the point at which the wall lifts significant distance to
become unstable, or develops a full stair-step diagonal crack. Based on these
definitions, the ductility factor of the wall is estimated to be eight.
Accounting for a factor of safety of two, it is recommended to use an R factor
of four.
8.
Conclusion
The
technology of Bisfoam-3 has proved its effectiveness in the repair and retrofit
of brick walls used as structural elements in historical buildings. In such
brick walls, the mortar has deteriorated to the level that it can be easily
removed by a pocketknife. The foam substitutes for the deteriorated mortar
joints. It makes the loose brick wall more monolithic and increases its
integrity. In addition, the ductile foam substitutes for the function of the
brittle mortar making the wall able to produce much more ductile response in
case of seismic ground motions. If the mortar joints are not deteriorated, then
they will break at very small deflections due to its brittle nature and
inability to carry large tension loads. The foam herein works as the second line
of defense that will pick up the lost function of the mortar but in a much more
ductile fashion allowing a better distribution and transfer of stresses in the
wall. Without the foam, a complete catastrophic failure is expected at
relatively much smaller deflections.
The
foam also has another important function. It provides a passive control of the
vibration of the wall by adding additional damping to the system. The increased
damping is resulting from the foam material itself in addition to the energy
dissipated in the friction between adjacent blocks of brick. The foam allows
more ductile response where various blocks of brick will have large relative
motion between them and as a result dissipating much more energy.
9.
References
·
Velazquez-Dimas,
J., Ehsani, M.R., and Saadatmanesh, H. (1998), “Cyclic Behavior of
Retrofitted URM Walls,” Proceedings, 2nd International Conference on Fiber
Composites in Infrastructure, Tucson, Arizona.
Figures
and Tables

Figure
1:
South Elevation of the LA City Hall


Figure
2:
Distribution of Holes on the Wall

Figure
3:
Pumping of Expansive Epoxy in the Wall


Reinforced concrete cap beam Reinforced concrete foundation Strong wall Strong floor Axial load Actuator Pinned-Pinned Steel ties

Figure
4:
Out-of-plane bending


Strong wall Reinforced concrete cap beam Reinforced concrete foundation Axial load Actuator Steel Reinforcement Strong floor
Figure
5:
In-plane Shear Test Set-up

Figure
6:
Load-Deflection Curve for Out-of-Plane Loading of Un-Injected Wall

Figure 7: Load Deflection Curve of the Out-of-Plane Repaired Wall (Phase I: Up to 1 inch Deflection)

Figure 8: Load-Deflection Curve of the Out-of-Plane Repaired Wall, (Phase II: Full Deflection Range)
![]() |
Figure 9: Failure Mechanism of the Out-Of-Plane Repaired Wall

Figure 10: Load-Deflection Curve of the Out-Of-Plane Retrofitted Wall

Figure 11: Failure of the Out-Of-Plane Retrofitted Wall
